Building an extension
Question
Make a precedence table showing the constraints for building an extension.
Activity | |
A | Get planning permission |
B | Build the foundations |
C | Build the walls |
D | Put in windows and doors |
E | Build the roof |
F | Put in electrics |
G | Put in plumbing |
H | Decorating |
Activity | A |
---|---|
Get planning permission |
Activity | B |
---|---|
Build the foundations |
Activity | C |
---|---|
Build the walls |
Activity | D |
---|---|
Put in windows and doors |
Activity | E |
---|---|
Build the roof |
Activity | F |
---|---|
Put in electrics |
Activity | G |
---|---|
Put in plumbing |
Activity | H |
---|---|
Decorating |
The constraints are:
- B depends on A
- C depends on B
- D and E depend on C
- F and G depend on E
- H depends on F and G
Activity | Depends on |
A | |
B | A |
C | B |
D | C |
E | C |
F | E |
G | E |
H | F and G |
Activity | A |
---|---|
Depends on |
Activity | B |
---|---|
Depends on | A |
Activity | C |
---|---|
Depends on | B |
Activity | D |
---|---|
Depends on | C |
Activity | E |
---|---|
Depends on | C |
Activity | F |
---|---|
Depends on | E |
Activity | G |
---|---|
Depends on | E |
Activity | H |
---|---|
Depends on | F and G |