M4 near Slough reopens after bridge work completed early

  • Published
New beams that form part of the bridge being put in placeImage source, Highways England
Image caption,

The steel beams will be part of the new Recreation Ground bridge near Slough

A stretch of the M4 in Berkshire has fully reopened after work to install steel beams that will form part of a new bridge was finished early.

The motorway between junctions 5 and 6, near Slough, reopened on Sunday at about 02:00 BST. It was due to be closed until 06:00 BST on Monday.

The beams will make up part of the new Recreation Ground bridge to link Datchet to Upper Court Park in Slough.

The M4 between junctions 3 and 12 is being upgraded to a smart motorway.

Work to install the beams was done within 24 hours, Highways England said.