Galashiels House site contamination sees cost rise

  • Published
Scottish Borders CouncilImage source, Google
Image caption,

Scottish Borders Council agreed to commit up to 拢1.8m to the scheme

A council has agreed to commit up to 拢1.8m to a housing development in the Borders after contamination issues emerged on the site.

Problems were found at the Langhaugh project in Galashiels during demolition and clearance works.

A report highlighted unforeseen costs to rid the site of asbestos which had not been apparent when it was bought.

Scottish Borders Council (SBC) agreed to approve the funding to allow the 39 home project to proceed.

Eildon Housing Association is behind the extra care housing scheme which it has been estimated will now cost over 拢7.6m.

It has secured more than 拢3.2m from private borrowing with the Scottish government providing 拢2.6m.

SBC will provide the remainder of the funding package after councillors agreed to follow officials' recommendations.