ý

Planning and organisationPlanning – planning the work

Volunteering in the local community is a rewarding experience. Setting appropriate aims and objectives, as well as applying project management skills, are part of the planning and organising process.

Part of National: Foundation KS4Community challenge

Planning – planning the work

A Gantt chart is a commonly used tool in project management. It was named after Henry Gantt, an American mechanical engineer who created the chart in the 1910s.

A Gantt chart is a type of bar chart. It is a visual representation of the project schedule, displayed as bars across a calendar. There are many free applications online which create Gantt charts. However, they can also be created non-electronically by hand following these steps.

Step one - Tasks

Come up with a list of tasks that need to be completed. These tasks should be very specific, so instead of just stating ‘meeting’, the task should state ‘meeting about finance’ or ‘meeting with venue organisers’.

Step two - Assign roles

Decide who can do each task and how long they need. The timings could be in hours or days. Initials are often used to show who is responsible for each task.

Step three - Build timelines

This means creating a table. In the table, the tasks should be listed (see step one) along with the timings and who is responsible (see step two). The table should look like this.

Table with column headers labelled as Task; Time needed; Responsibility

Step four - Decide on the task order

This means adding an extra column to the table, as shown here.

Table with column headers labelled as Task; Depends on; Time needed; Responsibility

If the project is about raising awareness for a local animal sanctuary, one of the tasks may involve designing publicity materials such as flyers and posters. However, another task may be to employ a printing company to produce them. This task cannot be completed until the first task has been achieved, as shown here. Also, if something is not applicable, it can be noted as n/a.

Table with column headers labelled as Task; Depends on; Time needed; Responsibility. Row one; 1. Design posters and flyer, n/a, 5 hours, JM. Row two;  2. Take to printing company; Task 1, 2 days, SD.

Example

This is an example of a Gantt chart.

In it, you will see that Task 1 has been scheduled to start on 21 March and to be completed by 24 March, so it will take three days.

Task 2 isn’t dependent on Task 1 being completed, so it can also start on 21 March. However, Task 2 takes until the 28 March, so it will take seven days.

Diagram for completing Tasks 1 - 7, between March 21 and April 4

Question

Look at the Gantt chart above. One task finishes on the same day as another starts. What day is this and what are the tasks?

More guides on this topic